Germany Cost per equivalent unit in process costing ( weighted average method )

Joined
Jun 23, 2019
Messages
1
Reaction score
0
Country
Germany
Hello guys !
Im struggling with an MC Question:
30. Under the weighted-average method, what are the costs per equivalent unit of “work done to date” for direct materials in June 2018?
A. $480.00
B. $550.00
C. $590.00
D. $673.50
the right answer is C. $590.00 but i dont understand why. The equivalent units of “work done to date” for direct materials in June 2018 are 32500 and the total Direct materials costs are $15,600,000. $15,600,000 / 32500 = 480. I would greatly appreciate if someone could help me ! Thanks in advance !
 

Attachments

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top