I am having trouble accounting for spoilage problems in my cost accounting class. I was hoping someone can please guide me on how to answer this type of problem. I get confused on the spoilage part as well as when the problem says that direct materials are added at the 50% point. What should I be looking for?
The answer is supposed to be C, but I don't know how to get that number. I have been trying for hours and some help would greatly be appreciated.
Beginning work in process consists of 7,000 units, 55% complete. 50,000 units were started and ending work in process is 5,000 units, 25% complete. Normal spoilage is equal to 10% of the units inspected. The inspection point occurs at the 20% point and 7,000 units were rejected. Direct materials are added at the 50% point, direct labour at 30% and overhead is applied uniformly. The costs per equivalent unit are: direct material $1.00; direct labour $1.50; overhead $2.00.
The cost of the ending work in process is:
a. $2,500
b. $2,850
c. $2,700
d. $4,000
The answer is supposed to be C, but I don't know how to get that number. I have been trying for hours and some help would greatly be appreciated.
Beginning work in process consists of 7,000 units, 55% complete. 50,000 units were started and ending work in process is 5,000 units, 25% complete. Normal spoilage is equal to 10% of the units inspected. The inspection point occurs at the 20% point and 7,000 units were rejected. Direct materials are added at the 50% point, direct labour at 30% and overhead is applied uniformly. The costs per equivalent unit are: direct material $1.00; direct labour $1.50; overhead $2.00.
The cost of the ending work in process is:
a. $2,500
b. $2,850
c. $2,700
d. $4,000